We are pleased to announced that construction work on Phase I of Switchback Apartments – Cantonments, is progressing steadily. Here’s what we’ve been up to:
Floor and wall tiling of the 4 storey building is 70% complete.
Internal plastering is about 90% done while external plastering is about 85% done.
Installation of glazed doors and windows are ongoing.
MEP first and second fixes installations, including mechanical, electrical, plumbing and AC installations are 80% complete.
Fixing of door frames is underway
Generator and Switch room is complete
External services (plumbing) has begun.
Concrete and iron works for underground water tank is complete.
Roofing work has been completed.
Health and Safety
We have taken precautions to ensure the safety of each worker during this Covid-19 pandemic. Our Health and Safety Officer ensure that controls within the Health and Safety plan are being strictly adhered to.
Park Apartments is almost sold out!
We hope you are as excited about our progress as we are! Although Phase I is sold out, you’ll be pleased to know we have a few units available in Phase II for offplan sale.
One bed apartments
We have only seven one bedroom apartments left for offplan sale! Standard and Deluxe options available.
Two bedroom apartments
Only six two bedroom apartments available and dwindling! Options also available in Standard and Deluxe.
Park Apartments is a great real estate investment opportunity with many benefits especially as a rental property.
Create generational wealth
Provides passive income for life
Can be used as leverage to buy more assets
Provides monthly cashflow
…. and many more!
Switchback Square is located at Switchback lane, Cantonments – Accra. Switchback Apartments are being developed by Mobus Properties Ghana. View our other developments here: www.mobusproperty.com